The last two weeks at The House that Convoy Built!

September 24, 2020

The last two weeks at The House that Convoy Built!

Week ending 17/9

  • Footings were poured by IRV Concreting (Dean and his team)
  • Reinforced with steel provided by A.R.C
  • Concrete pumped by the team at Wollongong Concrete Pumps
  • Concrete supply by Cleary Bros

 

Next week starting 18/9

  • Cross Excavations did final soil cleanup with the help of transport by MJ Rowles once again
  • All footings surveyed & pinned by Landteam Surveyors ready for block laying
  • Blockwork was delivered for retaining walls & ground floor internal walls by Baines Masonry
  • Blockwork hardware/sand and the cement will be delivered by Rowles Site Solutions
  • Over 1000 Blocks being laid by Rob Zakoc and the team at X Brick and Block laying Pty Ltd